When should an IT project turn red?

“When should an IT project turn red?” on TechTarget, 11/3/2026.

What evidence justifies escalation

A project often shows signs of trouble before missed deadlines or overruns make the problems obvious. Early warning signals can reveal that the plan no longer holds up.

Earned-value measures and cost and schedule variances can warn that performance is slipping against an approved plan. They do not necessarily reveal whether the original assumptions or business case still hold.

“These are typically lagging indicators,” explained Alan Zucker, an instructor at the University of Georgia. “Productivity, quality and staff turnover are examples of leading indicators.”

What a reset looks like in practice

“This made the project yellow from green, and that was healthy, as it allowed us to hit the right customers even if late, versus the wrong ones on time,” Kohli said. “We had to move design people into the team in a hurry and sacrifice or delay some other projects.”

A badly underestimated timeline can also force a reset. Zucker described leading an effort to develop a new financial reporting application.

“The technology team estimated it would take nine months to build. They were not even close. It took over two years,” he said.

Zucker said the team had to restructure the project several times, bringing in a new technology lead and shifting responsibilities from the technology to the business team.

“The application was finally deployed. It was a success and was used for the next decade,” Zucker said.